ROW Clearing Sec 7 - PAPC

SIZE: $27 million
DURATION: 2020 - 2022

Kyah Resources cleared 62 km of the Coastal GasLink Pipeline right-of-way through the challenging terrain of the rigged Coast Mountain Range. Kyah used various clearing methods to complete the work such as standard and steep slope harvesting equipment, helicopter logging, and hand falling, all without a single lost time incident. Kyah had to contend with environmentally sensitive areas including 17 Wetlands crossings, 94 Watercourses and multiple culturally sensitive areas with no incidents.